R82 Jumbo Hotfix Take 33

R82 Jumbo Hotfix Take 33

Download Jumbo Hotfix Accumulator Takes Download Previous Recommended Takes
Note - This Take contains all fixes from all earlier Takes.

Download CSV

ID Product Description
Take 33
Released on 08 July 2025 and declared as Recommended on 16 July 2025
Take 33 - Improvements and Resolved Issues
PRJ-62112,
PMTR-116903
VSNext In a VSNext setup, Virtual Gateways (except VS0) cannot establish SIC connectivity with the Security Management Server.
See the Critical Information section.
PRJ-62374,
PRHF-40338
Scalable Platforms The CPD process may exit during policy installation on a Scalable Platforms cluster on Quantum Force 29000 appliances.
PRJ-59589,
PMTR-114423
Scalable Platforms R81.20 / R81.10 / R81 Security Gateways, Cluster Members, and Scalable Platform Security Groups may fail to fetch the Threat Prevention policy from their R82 Security Management Server / Multi-Domain Security Management Server. See sk183602.

22 July 2026